Rue des Déportés Anderlechtois 19

Anderlecht · 01/AA/1762781 · Abattage d'arbres

Rue des Déportés Anderlechtois 19, Anderlecht: tree felling. Case octroyé, lodged on 12 October 2020. The decision was notified on 24 February 2022, 500 days after lodging.

vellen van 2 hoogstammige bomen
The application's own description, in its source language (NL). Source: Nova.
Key figures
Permit typeAbattage d'arbres
StatusOctroyé
Lodged on12 October 2020date the file was received
Decision notified24 February 2022500 days
Floor areasnot reported by the source
Competent authorityAnderlecht

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
13 mExtension or raisingconstruire une terrasse en façade arrière, au 1er étage2021
46 mHeavy renovationmettre en conformité le percement d'un mur porteur et le placement d'une poutre2021
57 mDemolition and reconstructionl'isolation de la façade côté rue de Veeweyde, des travaux d'aménagement intérieurs, la modification et l'isolation de l2025
63 mRegularisationrégulariser un immeuble de rapport (PV 2019/2180)2022
71 mExtension or raisingrégulariser la construction d’une annexe arrière au rez-de-chaussée, le percement du plancher pour l’installation d’un e2026

Other nearby cases : 01/PU/2015711, 01/PU/1997329, 01/PU/1931826, 01/PU/1867376, 01/SFD/1994381, 01/PU/1967147, 01/PU/1985861, 01/PU/1918128, 01/PU/1837763, 01/PU/1964059, 01/PU/1811319, 01/PU/1909544, 01/SFD/1961640, 01/PU/1868386, 01/PU/2032677, 01/GOU_PU/1855841, 01/PU/1904381, 01/PU/1960819, 01/GOU_PU/1896695, 01/PU/1940424, 01/PU/2014060, 01/PU/1893351, 01/PU/1953765, 01/PU/1827668, 01/PU/2011780

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)