Skip to content
AltUrb
Withdrawn

Rue Walcourt 205

Anderlecht · 01/CL2/2014086 · Permis d'environnement communal Classe 2

Rue Walcourt 205, Anderlecht: operation of installations. Case annulé, lodged on 18 November 1994.

etablir un atelier pour la trempe des métaux comportant 5 fours de 0.750 KW à 1.470 KW et une meule de 0.370 KW ainsi qu'un transformateur statique de 160 KVA
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'environnement communal Classe 2
StatusAnnulé
Lodged on18 November 1994date the file was received
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
40 mHeavy renovationmettre en conformité les deux duplex sous toiture et les aménagements en sous-sol d’un immeuble à appartements (modifica2024
47 mHeavy renovationmettre en conformité et transformer une maison unifamiliale2025
69 mExtension or raisingmettre en conformité la volumétrie existante et la toiture, transformer les espaces de vie, étendre latéralement l'exten2023
79 mNew constructionconstruire une maison unifamiliale2022
84 mHeavy renovationréaménager le rez-de-chaussée et aménagement de la zone de recul d’une maison d'habitation mitoyenne2026

Other nearby cases : 01/PU/1926041, 01/PU/1948930, 01/PU/1905256, 01/PU/1918966, 01/PU/2040425, 01/PU/1999482, 01/PU/1959266, 01/PU/1821867, 01/PU/1972716, 01/PU/2015088, 01/PU/1944240, 01/PFD/1934639, 01/PU/2029138, 01/PU/1858450, 01/PFD/2040080, 01/PU/1860954, 01/PU/1859730, 01/PU/1952739, 01/PFD/1903479, 01/PFD/1799744, 01/PU/1937892, 01/PU/2020521, 01/PU/1929231

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)