Square Albert Ier 1–28
Anderlecht · 01/CL3/1754986 · Déclaration préalable Communal
Square Albert Ier 1–28, Anderlecht: operation of installations. Case octroyé, lodged on 14 July 2020.
Exploiter un chantier| Permit type | Déclaration préalable Communal | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 14 July 2020 | date the file was received |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 79 m | Public space | Abattre trois érables en bordure du Square Albert 1er afin de pouvoir rénover un égout qui se situe en dessous. | 2026 |
| 115 m | Other | Régulariser des câbles aériens de fibre optique (télécommunication) dans plusieurs communes: 24 sites à Anderlecht ; 1 s | 2025 |
| 128 m | Extension or raising | Rénover et étendre une partie du bâtiment ainsi que l'aménagement d'une partie des espaces extérieurs et des abords immé | 2022 |
| 130 m | Demolition and reconstruction | transformer et étendre l'immeuble côté square Albert Ier afin d'y aménager 23 logements et 3 commerces pour une superfic | 2025 |
| 130 m | Demolition and reconstruction | démolir les bâtiments existants et construire un hôtel de 90 chambres au Square Albert Ier et un immeuble à appartements | 2023 |
Other nearby cases : 01/PU/1988591, 01/PU/1841880, 01/ECO/1830769, 01/PU/1967083, 01/PU/1825339, 01/PU/2043055, 01/GOU_PU/2019156, 01/PU/1994193, 01/PFD/1828280, 01/PU/1989826, 01/PU/1911165, 01/PU/1860429, 01/PU/1823231, 01/PFD/1850689, 01/PU/2028025, 01/PU/1956295, 01/PU/1909641, 01/PU/1937827, 01/PU/2032685, 01/PU/1945119, 01/PU/1994360, 01/PFD/1998354, 01/PU/1927298, 01/SFD/1993891, 01/PU/1966480
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)