Skip to content
AltUrb
Granted

Boulevard Industriel 137

Anderlecht · 01/CL3/1788475 · Déclaration préalable Communal

Boulevard Industriel 137, Anderlecht: operation of installations. Case octroyé, lodged on 4 June 2021.

exploiter un chantier de construction
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeDéclaration préalable Communal
StatusOctroyé
Lodged on4 June 2021date the file was received
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared complete

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
28 mNew constructionconstruire un hall industriel et des locaux d'activités productives2024
73 mExtension or raisingconstruire une extension d'un entrepôt2022
99 mHeavy renovationtransformer sans changement de volume le permis d'urbanisme 48388 (extension des WC Dames et mezzanine au rez-de-chaussé2023
100 mEnergy worksposer des installations techniques pour la recharge de voitures électriques2022
100 mEnergy worksplacer des installations techniques pour la recharge de voitures électriques2023

Other nearby cases : 01/PFD/1952064, 01/PU/1938453

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)