Granted
Avenue des Hortensias
Anderlecht · 01/IPE/1791530 · Permis d'environnement
Avenue des Hortensias, Anderlecht: operation of installations. Case octroyé, lodged on 28 June 2021. The decision was notified on 9 August 2022, 407 days after lodging.
Exploitation d'immeubles à appartements| Permit type | Permis d'environnement | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 28 June 2021 | date the file was received |
| Public inquiry | 10 December 2021 – 9 January 2022 | |
| Consultation committee | 20 January 2022 | |
| Decision notified | 9 August 2022 | 407 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 80 m | Change of use | modifier la destination des locaux situés au rez-de-chaussée du bâtiment F1 | 2024 |
| 80 m | Change of use | changer la destination des locaux du rez-de-chaussée de l'immeuble en locaux commerciaux | 2024 |
| 80 m | Change of use | changer la destination des locaux du rez-de-chaussée de l'immeuble en locaux commerciaux | 2024 |
| 93 m | New construction | Modifier le permis octroyé le 20/10/2025 pour la construction d’un immeuble de logements afin de l’adapter aux demandes | 2026 |
| 93 m | New construction | Het bouwen van een complex met 129 appartementen, een ondergrondse parkeergarage met 117 het aanleggen van de omgeving | 2023 |
Other nearby cases : 01/PU/1908905, 01/PU/1944831, 01/SFD/1957388, 01/SFD/1910056, 01/PU/1895336, 01/PFD/1909720, 01/PFD/1836663, 01/PFD/1991786
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)