Withdrawn
Route de Lennik 315
Anderlecht · 01/IPE/1811328 · Permis d'environnement
Route de Lennik 315, Anderlecht: operation of installations. Case annulé, lodged on 18 October 2021. The decision was notified on 16 June 2022, 241 days after lodging.
Exploitation d'un immeuble de logements et un parking souterrain| Permit type | Permis d'environnement | |
|---|---|---|
| Status | Annulé | |
| Lodged on | 18 October 2021 | date the file was received |
| Public inquiry | 13 April 2022 – 28 April 2022 | |
| Decision notified | 16 June 2022 | 241 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Decision notified · Withdrawn
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | New construction | construire un ensemble de 66 logements répartis sur 2 bâtiments reliés par une coursive extérieure; ainsi que 43 places | 2021 |
| 0 m | Façade and windows | Modifier le permis 01/PFD/1811561: changer certains aspects extérieurs et des éléments techniques (sans modification du | 2023 |
| 0 m | Student housing | Construire une immeuble de logements pour étudiants comprenant 28 unités de 5 chambres ou plus, des espaces communs, 1 a | 2025 |
| 0 m | Student housing | Construction d’une immeuble de logements pour étudiants, avec un total de 180 chambres d’étudiant, des espaces communes, | 2025 |
| 70 m | Retail or horeca fit-out | ouvrir un nouveau concept de cuisine rapide haut de gamme | 2021 |
Other nearby cases : 01/PFD/2042880, 01/PFD/1894840, 01/PFD/2017467, 01/PU/1936047, 01/AA/1958634, 01/PU/1930788, 01/PU/2015636, 01/AA/1851604, 01/PU/2010032, 01/PFD/1821515, 01/PFD/1994130, 01/PU/1823756
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)