Rue des Matériaux 14–16, Anderlecht: operation of installations. Case annulé, lodged on 9 December 2009. The decision was notified on 27 July 2010, 230 days after lodging.
40.A. Installations de combustion 900 kW, 68.B. Garage, emplacements couverts 111 places| Permit type | Permis d'environnement | |
|---|---|---|
| Status | Annulé | |
| Lodged on | 9 December 2009 | date the file was received |
| Public inquiry | 26 April 2010 – 27 April 2010 | |
| Decision notified | 27 July 2010 | 230 days |
| Works started | 1 August 2011 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Decision notified · Withdrawn
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 89 m | New construction | restructurer les espaces extérieurs du site Industrie, aménager et adapter les zones de parking, construire deux auvents | 2022 |
| 93 m | New construction | Construire un bâtiment scolaire modulaire temporaire comprenant 13 salles de classe, une réserve et de l'espace pour l'a | 2022 |
| 124 m | Regularisation | mettre en conformité un entrepôt | 2024 |
| 124 m | Other | mettre à jour administrativement les plans | 2023 |
| 124 m | Regularisation | mettre en conformité un entrepôt | 2025 |
Other nearby cases : 01/PU/2028025, 01/PFD/2024167, 01/PU/1841880, 01/PFD/1954938, 01/GOU_PU/2019156, 01/PU/1994193, 01/PU/2004115, 01/PFU/2003615, 01/PU/1988591, 01/PU/1909073, 01/PFD/2012738, 01/PFD/1992106, 01/PU/1993841, 01/PFD/1998351