Withdrawn

Boulevard Industriel 18

Anderlecht · 01/IPE/472855 · Permis d'environnement

Boulevard Industriel 18, Anderlecht: —. Case annulé, lodged on 23 July 2012. The decision was notified on 29 January 2013, 190 days after lodging.

02GSK
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'environnement
StatusAnnulé
Lodged on23 July 2012date the file was received
Public inquiry31 December 2012 – 15 January 2013
Decision notified29 January 2013190 days
Works started28 January 2013
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Public inquiry opened
  5. Public inquiry closed
  6. Works started
  7. Decision notified · Withdrawn

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mDemolition and reconstructionDémolir l’imprimerie et construire un pôle de logistique urbaine2026
74 mRetail or horeca fit-outplacer un show-case de 39m³2024
74 mOtherplacer un show-case de 39m³2025
161 mExtension or raisingRemplacer le parking étagé (non construit) par une extension du parking existant, ajouter un parking motos et un parking2022
161 mNew constructionPlacer 2 containers vestiaires/douches hommes et femmes pour une durée de limitée à 2 ans, le temps d'aménager des nouve2024

Other nearby cases : 01/PFD/1913329, 01/PFD/1834672, 01/PU/1931579

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)