Granted

Place de la Vaillance 24

Anderlecht · 01/IPE/494646 · Permis d'environnement

Place de la Vaillance 24, Anderlecht: operation of installations. Case octroyé, lodged on 26 November 2013. The decision was notified on 30 January 2014, 65 days after lodging.

L'exploitation d'une sous-station de métro
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'environnement
StatusOctroyé
Lodged on26 November 2013date the file was received
Decision notified30 January 201465 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared complete
  3. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
1 mChange of usemettre en conformité la façade et le changement d'utilisation au rez-de-chaussée de l'immeuble2023
55 mSplit into dwellingsmettre en conformité une lucarne arrière, une terrasse, un auvent et l'ajout de logement2022
55 mRoofmettre en conformité une lucarne arrière, une terrasse et un auvent2025
55 mRoofmettre en conformité une lucarne arrière, une terrasse et un auvent2025
55 mSplit into dwellingsaménager 3 logements2026

Other nearby cases : 01/PU/1971327, 01/PU/1831512, 01/PU/1911510, 01/PFU/1836035, 01/PFU/1930099, 01/PU/1913664, 01/PFU/2042888, 01/PU/1901588, 01/PU/1953429, 01/PFD/1957391, 01/PU/2008357, 01/PFU/2007573, 01/PU/1899360, 01/PFU/1948574, 01/SFD/2001609, 01/PU/1918978, 01/PU/1977903, 01/PU/1918999, 01/PU/1852499, 01/PU/1833467, 01/PU/2035500, 01/PU/1901768, 01/PU/1911481, 01/PU/1829845, 01/PU/1953765

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)