Granted
Boulevard Industriel 14
Anderlecht · 01/IPE/495451 · Permis d'environnement
Boulevard Industriel 14, Anderlecht: operation of installations. Case octroyé, lodged on 13 December 2013. The decision was notified on 18 December 2014, 370 days after lodging.
Nieuwe vergunning voor stelplaats autobussen (opslag en onderhoud)| Permit type | Permis d'environnement | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 13 December 2013 | date the file was received |
| Public inquiry | 27 August 2014 – 11 September 2014 | |
| Consultation committee | 17 September 2014 | |
| Decision notified | 18 December 2014 | 370 days |
| Works started | 12 December 2014 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Works started
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Extension or raising | Remplacer le parking étagé (non construit) par une extension du parking existant, ajouter un parking motos et un parking | 2022 |
| 0 m | New construction | Placer 2 containers vestiaires/douches hommes et femmes pour une durée de limitée à 2 ans, le temps d'aménager des nouve | 2024 |
| 0 m | Other | Aménager un parking pour 196 véhicules légers à l'air libre et pour 167 véhicules légers couverts | 2023 |
| 161 m | Demolition and reconstruction | Démolir l’imprimerie et construire un pôle de logistique urbaine | 2026 |
| 232 m | Retail or horeca fit-out | placer un show-case de 39m³ | 2024 |
Other nearby cases : 01/SFD/1986301
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)