Boulevard Industriel 130

Anderlecht · 01/IPE/578974 · Permis d'environnement

Boulevard Industriel 130, Anderlecht: operation of installations. Case octroyé, lodged on 24 August 2015. The decision was notified on 7 January 2016, 136 days after lodging.

demande de permis d’environnement pour une société de service spécialisée dans le dégraissage de pièces
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'environnement
StatusOctroyé
Lodged on24 August 2015date the file was received
Public inquiry27 October 2015 – 11 November 2015
Consultation committee26 November 2015
Decision notified7 January 2016136 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared complete
  3. Public inquiry opened
  4. Public inquiry closed
  5. Consultation committee
  6. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
88 mSigns and advertisingInstaller un dispositif publicitaire digital de 2 m² (MU783) à hauteur du n°122 boulevard Industriel 2023
137 mSigns and advertisingMaintenir un panneau publicitaire non éclairé de 20 m², situé sur un talus à proximité du boulevard Industriel 116.2024
165 mExtension or raisingconstruire une extension d'un entrepôt2022
189 mHeavy renovationtransformer sans changement de volume le permis d'urbanisme 48388 (extension des WC Dames et mezzanine au rez-de-chaussé2023
213 mNew constructionconstruire un hall industriel et des locaux d'activités productives2024

Other nearby cases : 01/PU/1908338

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)