Granted
Avenue Emile Gryson 1
Anderlecht · 01/IPEEXT/2008880 · Extension / Transformation de PE
Avenue Emile Gryson 1, Anderlecht: operation of installations. Case octroyé, lodged on 10 November 2025. The decision was notified on 11 December 2025, 31 days after lodging.
Ajout d'un site de compostage de déchets verts| Permit type | Extension / Transformation de PE | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 10 November 2025 | date the file was received |
| Decision notified | 11 December 2025 | 31 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 79 m | Heavy renovation | Aménager l'intérieurs pour le Centre de Technologies Avancées afin de créer un nouvel espace de formation « Salle & Bar | 2026 |
| 96 m | Roof | installer des dispositifs de sécurisation, remplacer une partie de la toiture, poser des panneaux photovoltaïques, régul | 2026 |
| 118 m | Roof | mettre en conformité le duplex 1 (rez-de-jardin & rez-de-chaussée) + agrandir les lucarnes sous-toiture pour le duplex 2 | 2023 |
| 126 m | Heavy renovation | réagencer un logement unifamilial, créer une rampe de garage et une terrasse côté jardin | 2022 |
| 130 m | Extension or raising | construire une annexe au rez-de-jardin et mettre en conformité les modifications en façade à rue d'une maison unifamilia | 2025 |
Other nearby cases : 01/PU/1915148, 01/PU/1866846, 01/PU/1828808, 01/AA/1831031, 01/PU/1856684, 01/PU/1927263, 01/PU/1979069, 01/PU/1834341, 01/PU/1800298, 01/PU/1834834, 01/PU/1826206
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)