Withdrawn
Boulevard Industriel 141
Anderlecht · 01/IPEEXT/450738 · Extension / Transformation de PE
Boulevard Industriel 141, Anderlecht: operation of installations. Case annulé, lodged on 19 April 2007. The decision was notified on 8 May 2007, 19 days after lodging.
parking à l'air libre de 17 emplacements| Permit type | Extension / Transformation de PE | |
|---|---|---|
| Status | Annulé | |
| Lodged on | 19 April 2007 | date the file was received |
| Decision notified | 8 May 2007 | 19 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Decision notified · Withdrawn
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 94 m | New construction | construire un hall industriel et des locaux d'activités productives | 2024 |
| 128 m | Energy works | poser des installations techniques pour la recharge de voitures électriques | 2022 |
| 128 m | Energy works | placer des installations techniques pour la recharge de voitures électriques | 2023 |
| 137 m | Extension or raising | construire une extension d'un entrepôt | 2022 |
| 181 m | Heavy renovation | transformer sans changement de volume le permis d'urbanisme 48388 (extension des WC Dames et mezzanine au rez-de-chaussé | 2023 |
Other nearby cases : 01/PFD/1847791
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)