Route de Lennik 808

Anderlecht · 01/IPEEXT/490190 · Extension / Transformation de PE

Route de Lennik 808, Anderlecht: operation of installations. Case octroyé, lodged on 22 July 2013. The decision was notified on 9 August 2013, 18 days after lodging.

Translation du projet, 50 mètres à l'Ouest du site initial
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeExtension / Transformation de PE
StatusOctroyé
Lodged on22 July 2013date the file was received
Decision notified9 August 201318 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.