Skip to content
AltUrb
Granted

Route de Lennik 808

Anderlecht · 01/IPEEXT/586707 · Extension / Transformation de PE

Route de Lennik 808, Anderlecht: —. Case octroyé, lodged on 1 December 2015. The decision was notified on 10 December 2015, 9 days after lodging.

ic ok
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeExtension / Transformation de PE
StatusOctroyé
Lodged on1 December 2015date the file was received
Decision notified10 December 20159 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)