Withdrawn

Boulevard Industriel 145

Anderlecht · 01/IPEEXT/595347 · Extension / Transformation de PE

Boulevard Industriel 145, Anderlecht: operation of installations. Case annulé, lodged on 8 March 2016. The decision was notified on 30 March 2016, 22 days after lodging.

Réactualisation et modification de nombreuses installations classées de l'usine
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeExtension / Transformation de PE
StatusAnnulé
Lodged on8 March 2016date the file was received
Decision notified30 March 201622 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Decision notified · Withdrawn

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
172 mEnergy worksposer des installations techniques pour la recharge de voitures électriques2022
172 mEnergy worksplacer des installations techniques pour la recharge de voitures électriques2023
219 mEnergy workstransformer des places de parking en places de recharges pour voitures électriques + installer 3 bornes de recharges éle2023
232 mNew constructionconstruire un hall industriel et des locaux d'activités productives2024
233 mPublic spaceAménager une zone d'amarrage d'un nouveau bateau de nettoyage qui permettre le chargement des déchets récoltés par le ba2022

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)