Granted
Rue des Matériaux 14–16
Anderlecht · 01/IPEEXT/660867 · Extension / Transformation de PE
Rue des Matériaux 14–16, Anderlecht: operation of installations. Case octroyé, lodged on 21 December 2017. The decision was notified on 28 February 2018, 69 days after lodging.
régularisation d’une unité de cogénération| Permit type | Extension / Transformation de PE | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 21 December 2017 | date the file was received |
| Decision notified | 28 February 2018 | 69 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 89 m | New construction | restructurer les espaces extérieurs du site Industrie, aménager et adapter les zones de parking, construire deux auvents | 2022 |
| 93 m | New construction | Construire un bâtiment scolaire modulaire temporaire comprenant 13 salles de classe, une réserve et de l'espace pour l'a | 2022 |
| 124 m | Regularisation | mettre en conformité un entrepôt | 2024 |
| 124 m | Other | mettre à jour administrativement les plans | 2023 |
| 124 m | Regularisation | mettre en conformité un entrepôt | 2025 |
Other nearby cases : 01/PU/2028025, 01/PFD/2024167, 01/PU/1841880, 01/PFD/1954938, 01/GOU_PU/2019156, 01/PU/1994193, 01/PU/2004115, 01/PFU/2003615, 01/PU/1988591, 01/PU/1909073, 01/PFD/2012738, 01/PFD/1992106, 01/PU/1993841, 01/PFD/1998351
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)