Granted
Boulevard Henri Simonet
Anderlecht · 01/IPEEXT/674318 · Extension / Transformation de PE
Boulevard Henri Simonet, Anderlecht: operation of installations. Case octroyé, lodged on 23 March 2018. The decision was notified on 24 April 2018, 32 days after lodging.
Modification du nombre et de la longueur des pieux géothermique| Permit type | Extension / Transformation de PE | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 23 March 2018 | date the file was received |
| Decision notified | 24 April 2018 | 32 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 158 m | Change of use | changer la destination au rez-de-chaussée de superficies pour bureaux et équipement vers superficies pour commerce et co | 2023 |
| 158 m | Change of use | changer la destination au rez-de-chaussée de superficies pour bureaux et équipement vers superficies pour commerce et co | 2023 |
| 168 m | New construction | Het bouwen van een complex met 129 appartementen, een ondergrondse parkeergarage met 117 het aanleggen van de omgeving | 2023 |
| 168 m | New construction | Modifier le permis octroyé le 20/10/2025 pour la construction d’un immeuble de logements afin de l’adapter aux demandes | 2026 |
| 204 m | Change of use | modifier la destination des locaux situés au rez-de-chaussée du bâtiment F1 | 2024 |
Other nearby cases : 01/PU/1954384, 01/SFD/1967344
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)