Withdrawn

Boulevard de l'Humanité 55

Anderlecht · 01/IPEEXT/685607 · Extension / Transformation de PE

Boulevard de l'Humanité 55, Anderlecht: operation of installations. Case annulé, lodged on 8 June 2018. The decision was notified on 4 July 2018, 26 days after lodging.

Extension pour suppression de groupe de froid au R22 avec nouveaux groupes de froid et déplacement d’armoires de sécurité concernant des STOCKS type 88 1A et 88 2A Modification des conditions d’exploiter relatives au stockage de substances dangereuses en armoire de sécurité et non en local de stockage
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeExtension / Transformation de PE
StatusAnnulé
Lodged on8 June 2018date the file was received
Decision notified4 July 201826 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Decision notified · Withdrawn

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
75 mRegularisationMise en conformité d'un bien suite à la réalisation de travaux.2021
75 mFaçade and windowsMettre en conformité la modification de la façade, la modification de la citerne et la non mise en œuvre de la toiture v2022
75 mRegularisationMise en conformité d'un bien suite à la réalisation de travaux.2022
75 mExtension or raisingrehausser la toiture du bâtiment, aménager une échelle à crinoline, réaménager la zone de recul et mettre en conformité 2024
209 mSigns and advertisingmaintenir un dispoisitif publicitaire de 36 m²2025

Other nearby cases : 01/PU/1989386