Withdrawn
Boulevard Industriel 20
Anderlecht · 01/IPEPLP/1776111 · Prolongation de PE
Boulevard Industriel 20, Anderlecht: operation of installations. Case annulé, lodged on 17 February 2021. The decision was notified on 17 November 2021, 273 days after lodging.
Exploitation d’un stockage de gaz, THT et compresseur| Permit type | Prolongation de PE | |
|---|---|---|
| Status | Annulé | |
| Lodged on | 17 February 2021 | date the file was received |
| Decision notified | 17 November 2021 | 273 days |
| Works started | 19 February 2022 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Withdrawn
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Demolition | Démolir deux gazomètres sphériques jusqu'au niveau du sol | 2022 |
| 128 m | Retail or horeca fit-out | placer un show-case de 39m³ | 2024 |
| 128 m | Other | placer un show-case de 39m³ | 2025 |
| 166 m | Demolition and reconstruction | Démolir l’imprimerie et construire un pôle de logistique urbaine | 2026 |
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)