Granted
Route de Lennik 276
Anderlecht · 01/IPEPLP/1931155 · Prolongation de PE
Route de Lennik 276, Anderlecht: operation of installations. Case octroyé, lodged on 1 February 2024. The decision was notified on 30 January 2025, 364 days after lodging.
Exploitation d’un immeuble de logement social| Permit type | Prolongation de PE | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 1 February 2024 | date the file was received |
| Decision notified | 30 January 2025 | 364 days |
| Works started | 4 February 2025 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 121 m | New construction | Construire 2 immeubles de logements comportant des parkings couverts et une surface commerciale au rez-de-chaussée de l' | 2025 |
| 124 m | Regularisation | Régulariser ces écarts au permis initial, concernant façades, volumes, accès, équipements et aménagements.Le projet Lenn | 2026 |
| 129 m | Split into dwellings | diviser la maison en deux unités de logements | 2026 |
| 153 m | Retail or horeca fit-out | aménager une activité commerciale de type restauration et un espace de coworking | 2023 |
| 153 m | Façade and windows | installer des volets et un store banne sur la terrasse | 2025 |
Other nearby cases : 01/GOU_PU/2009564, 01/PU/1972861, 01/PU/1916209, 01/PU/2017666, 01/PU/1930788, 01/AA/1958634, 01/PFD/2042880, 01/PU/1824486, 01/PFD/1942528, 01/PU/1974160, 01/PU/1860433, 01/PFD/1894840, 01/PU/1926922, 01/PFD/1963848
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)