Skip to content
AltUrb
Withdrawn

Rue Bara

Anderlecht · 01/IPEPLP/445704 · Prolongation de PE

Rue Bara, Anderlecht: —. Case annulé, lodged on 28 February 2005. The decision was notified on 20 July 2005, 142 days after lodging.

Key figures
Permit typeProlongation de PE
StatusAnnulé
Lodged on28 February 2005date the file was received
Decision notified20 July 2005142 days
Works started1 March 2006
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared complete
  3. Decision notified · Withdrawn
  4. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.