Boulevard Industriel 20
Anderlecht · 01/IPEPLP/447597 · Prolongation de PE
Boulevard Industriel 20, Anderlecht: —. Case annulé, lodged on 11 January 2006. The decision was notified on 22 May 2006, 131 days after lodging.
| Permit type | Prolongation de PE | |
|---|---|---|
| Status | Annulé | |
| Lodged on | 11 January 2006 | date the file was received |
| Decision notified | 22 May 2006 | 131 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Withdrawn
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Demolition | Démolir deux gazomètres sphériques jusqu'au niveau du sol | 2022 |
| 128 m | Retail or horeca fit-out | placer un show-case de 39m³ | 2024 |
| 128 m | Other | placer un show-case de 39m³ | 2025 |
| 166 m | Demolition and reconstruction | Démolir l’imprimerie et construire un pôle de logistique urbaine | 2026 |