Digue du Canal 40
Anderlecht · 01/IPEPLP/543904 · Prolongation de PE
Digue du Canal 40, Anderlecht: operation of installations. Case octroyé, lodged on 11 July 2014. The decision was notified on 5 May 2015, 298 days after lodging.
continuer à exploiter un hall industriel avec ateliers, dépôts et bureaux| Permit type | Prolongation de PE | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 11 July 2014 | date the file was received |
| Decision notified | 5 May 2015 | 298 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 77 m | Demolition | Démolition d'un bâtiment et ajout d'une clôture sur un terrain situé au numéro 1 de la Digue du canal. | 2022 |
| 85 m | Demolition | Démolir un bâtiment. | 2022 |
| 119 m | Operation of installations | permis à durée limitée (6 ans) pour stocker temporairement des déchets inertes et non dangereux dans des boxes délimités | 2026 |
| 125 m | New construction | construire un patio près de l'auditorium | 2025 |
| 161 m | Extension or raising | mettre en conformité la construction d'une annexe arrière sur 2 niveaux et la modification du nombre de logements | 2025 |
Other nearby cases : 01/PFD/1834619, 01/PU/2016015, 01/PU/2040443, 01/PFD/1991576, 01/PU/1996378, 01/PFD/1864579, 01/PFD/1865805, 01/PU/1823110, 01/PU/2034443, 01/PU/1823108, 01/PFD/1899879, 01/PFD/1896118, 01/PU/1826741, 01/PFD/1960867, 01/PFD/1853223, 01/PU/1828196