Withdrawn
Parc Zuun
Anderlecht · 01/IPETMP/1947776 · Permis d'environnement temporaire
Parc Zuun, Anderlecht: operation of installations. Case annulé, lodged on 12 June 2024. The decision was notified on 17 September 2024, 97 days after lodging.
Chantier amiante| Permit type | Permis d'environnement temporaire | |
|---|---|---|
| Status | Annulé | |
| Lodged on | 12 June 2024 | date the file was received |
| Decision notified | 17 September 2024 | 97 days |
| Works started | 30 September 2024 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared complete
- Decision notified · Withdrawn
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 90 m | Tree felling | Abattre et mettre en sécurité une saulaie et aménager un verger | 2022 |
| 90 m | Tree felling | Abattre et mettre en sécurité des arbres pour la sécurisation de la saulaie | 2022 |
| 174 m | Other | Installer et régulariser une station de télécommunication mobile sur un pylône existant rue de Zuen, au sein de la réser | 2025 |
| 175 m | Other | Implanter une éolienne de 149,5m de haut (sommet de la pale au zénith) comprenant la construction d'une cabine électriqu | 2022 |
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)