Granted
Avenue Emile Gryson 1
Anderlecht · 01/IPETMP/2041287 · Permis d'environnement temporaire
Avenue Emile Gryson 1, Anderlecht: operation of installations. Case octroyé, lodged on 7 August 2026. The decision was notified on 27 August 2026, 20 days after lodging.
Ceria - B9B - Désamiantage de colle noire zone hermétiquement fermée| Permit type | Permis d'environnement temporaire | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 7 August 2026 | date the file was received |
| Decision notified | 27 August 2026 | 20 days |
| Works started | 23 September 2026 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 110 m | Roof | installer des dispositifs de sécurisation, remplacer une partie de la toiture, poser des panneaux photovoltaïques, régul | 2026 |
| 140 m | Extension or raising | construire une annexe au rez-de-jardin et mettre en conformité les modifications en façade à rue d'une maison unifamilia | 2025 |
| 140 m | Extension or raising | construire une annexe et un escalier et aménager une terrasse à l'arrière d'une maison unifamiliale | 2023 |
| 147 m | Heavy renovation | réagencer un logement unifamilial, créer une rampe de garage et une terrasse côté jardin | 2022 |
| 163 m | Roof | mettre en conformité le duplex 1 (rez-de-jardin & rez-de-chaussée) + agrandir les lucarnes sous-toiture pour le duplex 2 | 2023 |
Other nearby cases : 01/PU/1868845, 01/PFD/2042158, 01/AA/1831031, 01/PU/1866846
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)