Boulevard Industriel

Anderlecht · 01/PFD/152269 · Permis d'urbanisme délivré par le FD

Boulevard Industriel, Anderlecht: tree felling. Case octroyé, lodged on 9 October 2003. The decision was notified on 14 November 2003, 36 days after lodging.

abattre 1 arbre
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme délivré par le FD
StatusOctroyé
Lodged on9 October 2003date the file was received
Decision notified14 November 200336 days
Floor areasnot reported by the source
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared complete
  3. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.