Granted
Rue des Deux Gares 128
Anderlecht · 01/PFD/160242 · Permis d'urbanisme délivré par le FD
Rue des Deux Gares 128, Anderlecht: new construction. Case octroyé, lodged on 10 December 2004. The decision was notified on 27 July 2006, 594 days after lodging.
- démolir 4 bâtiments annexes désaffectés et un atelier de menuiserie
- transformer le bâtiment de l'économat en Centre Logistique Infrastructure et Magasin FM.
- modifier le tracé des voies et du relief
- construire 2 zones de stockage pour chantier| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 10 December 2004 | date the file was received |
| Public inquiry | 23 April 2006 – 8 May 2006 | |
| Consultation committee | 17 May 2006 | |
| Decision notified | 27 July 2006 | 594 days |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.