Rue des Deux Gares 128

Anderlecht · 01/PFD/160242 · Permis d'urbanisme délivré par le FD

Rue des Deux Gares 128, Anderlecht: new construction. Case octroyé, lodged on 10 December 2004. The decision was notified on 27 July 2006, 594 days after lodging.

- démolir 4 bâtiments annexes désaffectés et un atelier de menuiserie - transformer le bâtiment de l'économat en Centre Logistique Infrastructure et Magasin FM. - modifier le tracé des voies et du relief - construire 2 zones de stockage pour chantier
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme délivré par le FD
StatusOctroyé
Lodged on10 December 2004date the file was received
Public inquiry23 April 2006 – 8 May 2006
Consultation committee17 May 2006
Decision notified27 July 2006594 days
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared complete
  3. Public inquiry opened
  4. Public inquiry closed
  5. Consultation committee
  6. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)