Granted
Boulevard Industriel 17
Anderlecht · 01/PFD/1761306 · Permis d'urbanisme délivré par le FD
Boulevard Industriel 17, Anderlecht: public space. Case octroyé, lodged on 25 September 2020. The decision was notified on 24 February 2021, 152 days after lodging.
Voorzien van infrastructuurwerken in het bestaande ontspanningsstation Anderlecht (C.G.B.)| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 25 September 2020 | date the file was received |
| Decision notified | 24 February 2021 | 152 days |
| Works started | 12 April 2021 | |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 165 m | Retail or horeca fit-out | placer un show-case de 39m³ | 2024 |
| 165 m | Other | placer un show-case de 39m³ | 2025 |
| 177 m | Demolition | Démolir deux gazomètres sphériques jusqu'au niveau du sol | 2022 |
| 206 m | Change of use | transformer une unité productive et une partie d'unité productive au rez-de-chaussée en crèche de 4 sections de 18 enfan | 2026 |
| 222 m | Change of use | changement d’utilisation de Retail en restaurant brasserie | 2024 |
Other nearby cases : 01/PFD/1897668, 01/PFD/2032450
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)