Skip to content
AltUrb
Granted

Rue des Deux Gares 128

Anderlecht · 01/PFD/1924887 · Permis d'urbanisme délivré par le FD

Rue des Deux Gares 128, Anderlecht: change of use. Case octroyé, lodged on 1 December 2023. The decision was notified on 17 September 2024, 291 days after lodging.

Changer l’affectation de locaux de formation en laboratoire de matériaux et construire un local de stockage.
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme délivré par le FD
StatusOctroyé
Lodged on1 December 2023date the file was received
Public inquiry21 May 2024 – 20 June 2024
Consultation committee27 June 2024
Decision notified17 September 2024291 days
Works started26 February 2024
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Works started
  4. Declared complete
  5. Public inquiry opened
  6. Public inquiry closed
  7. Consultation committee
  8. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
155 mSigns and advertisingMaintenir un panneau publicitaire non éclairé de 36m², situé sur un talus à proximité de la Rue de la Petite-Île n° 128.2024
200 mStudent housingDémolir un hangar commercial et construire un immeuble comprenant 306 logements étudiants (176 studios conventionnées et2025
209 mNew constructiondemande initiale :aménager un nouveau quartier 'Petite-île/ Citygate II' comportant 254 logements sociaux, 109 logements2021
210 mPublic spaceApporter une modification mineure à un îlot de circulation existant dans la Rue des Deux Gares, afin de permettre un acc2024

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)