Skip to content
AltUrb
Granted

Boulevard Industriel

Anderlecht · 01/PFD/406976 · Permis d'urbanisme délivré par le FD

Boulevard Industriel, Anderlecht: public space. Case octroyé, lodged on 28 September 2011. The decision was notified on 28 March 2012, 182 days after lodging.

rénover les voiries du site ' Quai d'Aa'
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme délivré par le FD
StatusOctroyé
Lodged on28 September 2011date the file was received
Public inquiry31 October 2011 – 30 November 2011
Consultation committee8 December 2011
Decision notified28 March 2012182 days
Floor areasnot reported by the source
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared complete
  3. Public inquiry opened
  4. Public inquiry closed
  5. Consultation committee
  6. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)