Granted
Avenue Emile Gryson
Anderlecht · 01/PFD/543430 · Permis d'urbanisme délivré par le FD
Avenue Emile Gryson, Anderlecht: new construction. Case octroyé, lodged on 9 July 2014. The decision was notified on 18 November 2015, 497 days after lodging.
Construire 2 bâtiments (vestiaires et réserves) et aménager 2 terrains de football en revêtement synthétique| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 9 July 2014 | date the file was received |
| Public inquiry | 17 June 2015 – 2 July 2015 | |
| Consultation committee | 9 July 2015 | |
| Decision notified | 18 November 2015 | 497 days |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 203 m | Other | Implanter une éolienne de 149,5m de haut (sommet de la pale au zénith) comprenant la construction d'une cabine électriqu | 2022 |
| 231 m | Tree felling | abattre un arbre à haute tige | 2022 |
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)