Skip to content
Altaica Urban
Granted

Avenue d'Itterbeek 550

Anderlecht · 01/PFD/650859 · Permis d'urbanisme délivré par le FD

Avenue d'Itterbeek 550, Anderlecht: new construction. Case octroyé, lodged on 8 September 2017. The decision was notified on 2 May 2019, 601 days after lodging.

Bouwen van een nieuwe vrijstaande middenspanningscabine.
The application's own description, in its source language (NL). Source: Nova.
Key figures
Permit typePermis d'urbanisme délivré par le FD
StatusOctroyé
Lodged on8 September 2017date the file was received
Public inquiry27 November 2018 – 18 December 2018
Consultation committee20 December 2018
Decision notified2 May 2019601 days
Floor areasnot reported by the source
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared complete
  3. Public inquiry opened
  4. Public inquiry closed
  5. Consultation committee
  6. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
83 mNew constructionaménager des terrains de football couverts avec installation de vestiaires et autres aménagements dont a besoin l'organi2023
109 mExtension or raisingRénovation et agrandissement des cours de récréation, création d’un jardin potager Agrandissement du préau et pose de br2024
109 mExtension or raisingRénover et agrandir les cours de récréation, créer un jardin potager Agrandir le préau et poser un brise-soleil Rénover 2024
179 mNew constructionConstruire un abri à vélos de 25 places2025
179 mNew constructionConstruire un abri à vélos de 25 places2025

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)