Granted
Rue de Zuen 38–42
Anderlecht · 01/PFU/283516 · Permis d'urbanisme unique délivré par le FD
Rue de Zuen 38–42, Anderlecht: operation of installations. Case octroyé, lodged on 15 June 2010. The decision was notified on 13 May 2011, 332 days after lodging.
Gebruik van een terrein voor de ontwatering van baggerslib. Tijdelijke activiteit (6 maanden)| Permit type | Permis d'urbanisme unique délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 15 June 2010 | date the file was received |
| Public inquiry | 24 February 2011 – 11 March 2011 | |
| Consultation committee | 17 March 2011 | |
| Decision notified | 13 May 2011 | 332 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 76 m | Other | Installer et régulariser une station de télécommunication mobile sur un pylône existant rue de Zuen, au sein de la réser | 2025 |
| 202 m | Tree felling | Abattre et mettre en sécurité une saulaie et aménager un verger | 2022 |
| 202 m | Tree felling | Abattre et mettre en sécurité des arbres pour la sécurisation de la saulaie | 2022 |
| 216 m | Energy works | aménager une infrastructure de recharge comprenant 5 chargeurs rapides et 30 chargeurs lents, avec les abris et la cabin | 2024 |
| 216 m | Extension or raising | construire une extension de plain-pieds de 414 m² de l'entrepôt du bâtiment IKEA, ainsi que d'un auvent de 65 m², pour l | 2026 |
Other nearby cases : 01/GOU_PU/1829433