Skip to content
AltUrb
Granted

Route de Lennik 808

Anderlecht · 01/PFU/488468 · Permis d'urbanisme unique délivré par le FD

Route de Lennik 808, Anderlecht: new construction. Case octroyé, lodged on 12 June 2013. The decision was notified on 7 February 2014, 240 days after lodging.

Modifier l’implantation de la construction du nouvel Institut Jules Bordet sur le site du Campus Universitaire, en bordure de la rue Meylemeersch (permis modificatif du PU 403187).
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme unique délivré par le FD
StatusOctroyé
Lodged on12 June 2013date the file was received
Public inquiry18 September 2013 – 3 October 2013
Consultation committee24 October 2013
Decision notified7 February 2014240 days
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared complete
  3. Public inquiry opened
  4. Public inquiry closed
  5. Consultation committee
  6. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)