Granted
Digue du Canal 1–3
Anderlecht · 01/PU/1748755 · Permis d'urbanisme privé
Digue du Canal 1–3, Anderlecht: demolition. Case octroyé, lodged on 13 May 2020. The decision was notified on 19 November 2020, 190 days after lodging. It removes 137 m² of office space.
démolir des cuves et des bâtiments annexe137m²
Office floor area removed
| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 13 May 2020 | date the file was received |
| Decision notified | 19 November 2020 | 190 days |
| Works started | 30 November 2020 | |
| Competent authority | Anderlecht |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
- Works started
- event_works_ended
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Operation of installations | permis à durée limitée (6 ans) pour stocker temporairement des déchets inertes et non dangereux dans des boxes délimités | 2026 |
| 95 m | Demolition | Démolition d'un bâtiment et ajout d'une clôture sur un terrain situé au numéro 1 de la Digue du canal. | 2022 |
| 124 m | Demolition | Démolir un bâtiment. | 2022 |
| 160 m | Subdivision | Aménager une voirie privée interne dans le cadre du permis de lotir PL 3/GL/101_00 "lot voirie" | 2024 |
| 162 m | New construction | construire un patio près de l'auditorium | 2025 |
Other nearby cases : 01/PU/1945702, 01/GOU_PU/1953855, 01/PU/1852396, 01/PU/1850280, 01/SFD/1944143, 01/PU/1862281, 01/PFD/1942001, 01/PU/1973474, 01/PFD/1865805
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)