Rue de l'Ile Ste Hélène 18
Anderlecht · 01/PU/1823277 · Permis d'urbanisme privé
Rue de l'Ile Ste Hélène 18, Anderlecht: new construction. Case octroyé, lodged on 24 November 2021. The decision was notified on 28 April 2022, 155 days after lodging.
plaatsen van een prefab hoogspanningscabine| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 24 November 2021 | date the file was received |
| Decision notified | 28 April 2022 | 155 days |
| Works started | 6 May 2022 | |
| Competent authority | Anderlecht |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Regularisation | mettre en conformité certains revêtements (perméables) | 2026 |
| 84 m | Extension or raising | agrandir le logement existant en créant une extension en toiture, changer les châssis | 2023 |
| 88 m | Extension or raising | créer une issue et un escalier extérieur de secours | 2022 |
| 184 m | Change of use | changer l'affectation d'espaces de bureaux en espace de stockage (maintien d'un espace bureaux au rez-de-chaussée) | 2025 |
| 206 m | Tree felling | abattre 68 arbres le long des berges de la Senne | 2021 |
Other nearby cases : 07/PFD/1963444