Granted
Chaussée de Mons 1253
Anderlecht · 01/PU/1899256 · Permis d'urbanisme privé
Chaussée de Mons 1253, Anderlecht: energy works. Case octroyé, lodged on 25 April 2023. The decision was notified on 22 January 2024, 272 days after lodging.
placer des installations techniques pour la recharge de voitures électriques| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 25 April 2023 | date the file was received |
| Decision notified | 22 January 2024 | 272 days |
| Floor areas | — | not reported by the source |
| Competent authority | Anderlecht |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 54 m | Demolition and reconstruction | régulariser l'annexe arrière au rez-de-chaussée, démolir la seconde annexe arrière, mettre en conformité la situation ex | 2025 |
| 54 m | Façade and windows | régulariser et isoler les annexes arrières au rez-de-chaussée + mettre à jour les plans de la maison (PV I-2022/4099) | 2024 |
| 57 m | Extension or raising | mettre en conformité une extension au rez-de-chaussée en façade arrière | 2022 |
| 83 m | Demolition and reconstruction | Démolir une maison avec entrepôt et construire des immeubles neufs sur les lots 1 à 4 (PL: 01/LPFD/621051), comprenant 1 | 2024 |
| 123 m | Regularisation | mettre en conformité une maison unifamiliale | 2023 |
Other nearby cases : 01/PU/1984341, 01/GOU_PU/2009564, 01/PU/1925386, 01/PU/1972861, 01/PFD/1966645, 01/GOU_PU/1945105, 01/PU/1991181, 01/PU/1848830, 01/PU/1960218, 01/PU/1799500, 01/PFD/1975944, 01/PU/1822591, 01/PU/1911104, 01/PFD/1912389, 01/PU/1848815, 01/PU/1829749, 01/PU/1911564, 01/PU/1826206, 01/PU/2017666, 01/PU/1949015
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)