Rue Polydore Moerman 10
Anderlecht · 01/PU/1907873 · Permis d'urbanisme privé
Rue Polydore Moerman 10, Anderlecht: split into dwellings. Case octroyé, lodged on 12 July 2023. The decision was notified on 12 January 2024, 184 days after lodging. The project creates 33 m² of housing. It comprises 1 dwellings.
transformer un immeuble de rapport avec ajout d'une unité d'habitation| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 12 July 2023 | date the file was received |
| Decision notified | 12 January 2024 | 184 days |
| Works started | 10 March 2025 | |
| Competent authority | Anderlecht |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Extension or raising | construire une extension au niveau jardin (R+1), ajouter des terrasses aux étages en façade arrière, transformer l'étage | 2024 |
| 0 m | Heavy renovation | transformer un immeuble | 2024 |
| 0 m | Extension or raising | construire des terrasses en façade arrière pour les appartements du R+2 et R+3, mettre en conformité la hauteur du faît | 2025 |
| 31 m | Extension or raising | Mettre en conformité un immeuble de rapport (nombre de logement, extension arrière et châssis en façade avant | 2025 |
| 37 m | Tree felling | abattre un arbre à haute tige | 2024 |
Other nearby cases : 01/PU/1907130, 01/PU/1845174, 01/PU/2028454, 01/PU/1964592, 01/PU/2015931, 01/PU/1999423, 01/PU/1965169, 01/PU/1999176, 01/PU/1848973, 01/PU/2040679, 01/PU/2044860, 01/PU/1823658, 01/PU/2009602, 01/PU/1918344, 01/PU/1966806, 01/GOU_PU/1862144, 01/PU/1911722, 01/SFD/1894775, 01/GOU_PU/1903173, 01/PU/1843315, 01/PU/1850144, 01/PU/1846026, 01/PU/1986176, 01/PU/1938546, 01/PU/1990021