Granted
Rue des Matériaux Section B n° 108i
Anderlecht · 01/PU/2007393 · Permis d'urbanisme privé
Rue des Matériaux Section B n° 108i, Anderlecht: demolition and reconstruction. Case octroyé, lodged on 15 November 1923. The decision was notified on 28 January 1924, 74 days after lodging.
démolir un garage et construire deux magasins| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 15 November 1923 | date the file was received |
| Decision notified | 28 January 1924 | 74 days |
| Floor areas | — | not reported by the source |
| Competent authority | Anderlecht |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | New construction | Construire un bâtiment scolaire modulaire temporaire comprenant 13 salles de classe, une réserve et de l'espace pour l'a | 2022 |
| 109 m | Public space | Abattre trois érables en bordure du Square Albert 1er afin de pouvoir rénover un égout qui se situe en dessous. | 2026 |
| 123 m | Façade and windows | Rénovation énergétique complète de toutes les façades du campus KAAI de la Haute Ecole Erasmus de Bruxelles | 2025 |
| 141 m | New construction | restructurer les espaces extérieurs du site Industrie, aménager et adapter les zones de parking, construire deux auvents | 2022 |
| 172 m | Heavy renovation | transformer et mettre en conformité un immeuble de rapport | 2022 |
Other nearby cases : 01/PU/1909073, 01/PFD/2012738, 01/PU/1988591, 01/PU/2028025, 01/PU/1966480, 01/PU/1927298, 01/SFD/1993891, 01/PU/1994193, 01/GOU_PU/2019156, 01/PU/1967083, 01/PFU/2003615, 01/PU/2004115, 01/PFD/1954938
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)