Boulevard Poincaré 31
Anderlecht · 01/PU/2021207 · Permis d'urbanisme privé
Boulevard Poincaré 31, Anderlecht: heavy renovation. Case octroyé, lodged on 19 December 1921. The decision was notified on 17 January 1922, 29 days after lodging.
effectuer des transformations dans les dépendances de l'usine (boulevard d'Anderlecht, 31)| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 19 December 1921 | date the file was received |
| Decision notified | 17 January 1922 | 29 days |
| Floor areas | — | not reported by the source |
| Competent authority | Anderlecht |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 29 m | Façade and windows | régularisation du conduit d'évacuation de la hotte sur la façade arrière | 2022 |
| 29 m | Extension or raising | mettre en conformité la rehausse de la toiture arrière | 2022 |
| 37 m | Split into dwellings | mettre en conformité la modification de la façade à rue, l'ajout d'un logement et des travaux au rez-de-chaussée commerc | 2022 |
| 37 m | Split into dwellings | mettre en conformité la modification de la façade à rue, l'ajout d'un logement et des travaux au rez-de-chaussée commerc | 2024 |
| 51 m | Façade and windows | isoler la façade arrière, la façade pignon et la toiture | 2023 |
Other nearby cases : 01/SFD/1945354, 01/GOU_PU/1951830, 01/PU/1865915, 01/PU/1969763, 01/PU/1811603, 01/GOU_PU/1930709, 01/PU/1865922, 01/SFD/1922730, 04/PFU/1926075, 04/PFU/1998416, 01/GOU_PU/1858115, 01/PU/1851710, 01/PU/1821878, 01/PU/1868372, 01/GOU_PU/1856468, 01/SFD/1908278, 01/PU/1996104, 01/PU/1826539, 04/SFD/1841434, 04/PFD/1825950, 01/PU/1854309, 01/PFD/1853132, 01/PU/2004762, 04/PU/1820333, 04/PU/1964930