Refused
Boulevard Industriel 99
Anderlecht · 01/SFD/1979420 · Permis d'urbanisme – saisine du fonctionnaire délégué
Boulevard Industriel 99, Anderlecht: demolition and reconstruction. Case refusé, lodged on 1 April 2025. The decision was notified on 16 May 2025, 45 days after lodging.
remplacer la friterie existante par une friterie container| Permit type | Permis d'urbanisme – saisine du fonctionnaire délégué | |
|---|---|---|
| Status | Refusé | |
| Lodged on | 1 April 2025 | date the file was received |
| Public inquiry | 8 April 2025 – 23 April 2025 | |
| Consultation committee | 24 April 2025 | |
| Decision notified | 16 May 2025 | 45 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Refused
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Retail or horeca fit-out | remplacer la friterie existante par une friterie container | 2024 |
| 51 m | Change of use | changer l'affectation de l'entrepôt et de l'étage en grand commerce spécialisé | 2023 |
| 81 m | Energy works | installer une cabine moyenne tension et des bornes de recharge pour véhicules électriques | 2023 |
| 108 m | Extension or raising | étendre un entrepôt existant | 2023 |
| 114 m | Signs and advertising | maintenir un dispoisitif publicitaire de 36 m² | 2025 |
Other nearby cases : 01/PU/1989386, 01/PU/1908338, 01/PU/1821987, 01/PFD/1799744, 01/PFD/1966649