Avenue des Volontaires 103
Auderghem · 02/IPEPLP/1775055 · Prolongation de PE
Avenue des Volontaires 103, Auderghem: operation of installations. Case octroyé, lodged on 5 February 2021. The decision was notified on 9 August 2021, 185 days after lodging.
Uitbating van een tankstation
| Permit type | Prolongation de PE | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 5 February 2021 | date the file was received |
| Decision notified | 9 August 2021 | 185 days |
| Works started | 7 February 2022 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Signs and advertising | remplacer 2 enseignes pour une station service ESSO | 2024 |
| 34 m | Demolition and reconstruction | démolir et reconstruire la véranda, mettre en conformité une baie intérieure et les façades d'une maison unifamiliale | 2024 |
| 48 m | Roof | construire une toiture à versants avec lucarnes et régulariser la modification des châssis et de la porte de garage d’un | 2023 |
| 50 m | Façade and windows | remplacer les châssis et la porte de garage ainsi qu'installer une baie vitrée | 2026 |
| 61 m | Heavy renovation | transformer et mettre en conformité une maison unifamiliale | 2023 |
Other nearby cases : 05/PU/2031711, 05/PU/1966813, 02/PU/1983693, 02/PU/1904426, 05/PU/1932254, 02/PU/1978821, 02/PU/1970004, 02/PU/1954594, 05/PU/2032653, 02/PU/1847651, 05/PU/1968468, 05/PU/2005435, 05/PU/1926707, 02/PU/1926482, 02/PU/1936359, 02/PU/1839722, 05/PU/1907681, 05/PU/1957191, 05/PU/1970384, 05/PU/1924122, 05/PU/1833324, 02/PU/1962479, 02/PU/1972756, 02/PU/1995451, 19/PU/2007463
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)