Boulevard du Souverain 240
Auderghem · 02/IPEPLP/464989 · Prolongation de PE
Boulevard du Souverain 240, Auderghem: operation of installations. Case octroyé, lodged on 24 April 2012. The decision was notified on 15 March 2013, 325 days after lodging.
Prolongation de permis d'environnement pour une station-service| Permit type | Prolongation de PE | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 24 April 2012 | date the file was received |
| Decision notified | 15 March 2013 | 325 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 72 m | Extension or raising | agrandir et transformer une maison unifamiliale | 2022 |
| 73 m | Demolition | SANS SUITE démolir une maison | 2025 |
| 73 m | Demolition | Afbraak woning | 2025 |
| 99 m | Façade and windows | mettre en conformité l'isolation thermique par l’extérieur sur une partie de la façade | 2026 |
| 104 m | Extension or raising | pour créer une extension au 2ème étage d'une maison unifamiliale mitoyenne | 2021 |
Other nearby cases : 02/GOU_PU/1870552, 02/ENS/1841270, 02/PU/1841230, 02/PU/1847415, 02/PU/1922659, 02/ENS/1966796, 02/PU/1913304, 02/ENS/1829679, 02/PU/1928147, 02/PU/2042028, 02/CPFD/1932694, 02/PFD/1930464, 02/PU/1833449, 02/PU/1953202, 02/PU/1959197, 02/PFD/1946025, 02/PU/1925153, 02/SFD/1827864, 02/PU/1828260, 02/PFD/1962552, 02/GOU_PU/1835667, 02/PU/1801301, 02/GOU_PU/1987259, 02/PU/1952616, 02/PU/2018401
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)