Skip to content
Altaica Urban
Withdrawn

Avenue de la Sablière 2

Auderghem · 02/IPETMP/601870 · Permis d'environnement temporaire

Avenue de la Sablière 2, Auderghem: operation of installations. Case annulé, lodged on 1 June 2016. The decision was notified on 14 October 2016, 135 days after lodging.

Asbestwerf
The application's own description, in its source language (NL). Source: Nova.
Key figures
Permit typePermis d'environnement temporaire
StatusAnnulé
Lodged on1 June 2016date the file was received
Decision notified14 October 2016135 days
Works started31 October 2016
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Withdrawn
  5. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)