Granted
Autoroute E411
Auderghem · 02/PFD/182969 · Permis d'urbanisme délivré par le FD
Autoroute E411, Auderghem: new construction. Case octroyé, lodged on 11 June 2007. The decision was notified on 16 June 2008, 371 days after lodging.
Créer un entrepôt, des boxes de stockage, et 29 (38) emplacements de parking non couverts| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 11 June 2007 | date the file was received |
| Public inquiry | 2 November 2007 – 17 November 2007 | |
| Consultation committee | 29 November 2007 | |
| Decision notified | 16 June 2008 | 371 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)