Avenue Herrmann-Debroux, Auderghem: public space. Case octroyé, lodged on 10 October 2011. The decision was notified on 29 November 2011, 50 days after lodging.
Modifier le PU 02/pfd/283146 délivré le 13/12/2010 en modifiant l'implantation de l'édicule-ascenseur en surface| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 10 October 2011 | date the file was received |
| Decision notified | 29 November 2011 | 50 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.