Granted
Avenue de la Houlette 95
Auderghem · 02/PFD/560297 · Permis d'urbanisme délivré par le FD
Avenue de la Houlette 95, Auderghem: new construction. Case octroyé, lodged on 11 March 2015. The decision was notified on 4 February 2016, 330 days after lodging. The project creates 847 m² of housing. It creates 793 m² of office space. It comprises 16 dwellings.
Construire un immeuble de 16 appartements comportant les bureaux du CPAS au rez-de-chaussée et au 1° étage ainsi que 12 parking en sous-sol ( phase 2) en extenssion de l'immeuble existant (phase1)847m²
Housing floor area created
793m²
Office floor area created
16
Dwellings created
| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 11 March 2015 | date the file was received |
| Public inquiry | 22 October 2015 – 6 November 2015 | |
| Consultation committee | 19 November 2015 | |
| Decision notified | 4 February 2016 | 330 days |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.