Granted
Rouge-Cloître
Auderghem · 02/PFU/403878 · Permis d'urbanisme unique délivré par le FD
Rouge-Cloître, Auderghem: other. Case octroyé, lodged on 23 May 2011. The decision was notified on 7 July 2011, 45 days after lodging.
Aménager une zone de stockage des déchets sur le site du Rouge-Cloître| Permit type | Permis d'urbanisme unique délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 23 May 2011 | date the file was received |
| Decision notified | 7 July 2011 | 45 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)