Skip to content
AltUrb
Granted

Boulevard Général Jacques

Auderghem · 02/PFU/463693 · Permis d'urbanisme unique délivré par le FD

Boulevard Général Jacques, Auderghem: heavy renovation. Case octroyé, lodged on 21 March 2012. The decision was notified on 13 June 2013, 449 days after lodging. The project creates 120 m² of housing.

Transformer un ensemble de trois immeubles de logements. (Modification du permis 02/PFU/197024)
The application's own description, in its source language (FR). Source: Nova.
120
Housing floor area created
Key figures
Permit typePermis d'urbanisme unique délivré par le FD
StatusOctroyé
Lodged on21 March 2012date the file was received
Public inquiry30 August 2012 – 14 September 2012
Consultation committee11 October 2012
Decision notified13 June 2013449 days
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared complete
  3. Public inquiry opened
  4. Public inquiry closed
  5. Consultation committee
  6. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)